    8 October 2018

    Construction for Blue at Lavender Bay commences in October 2018.

    • Construction Certificate approval was obtained in August 2018 to commence demolition works.
    • Demolition works commence in October 2018.  Activities involve:
      • Services decommissioning. 
      • Removal of internal finishes, ceilings, partitions & furniture.
      • Demolition of ground floor and basement areas, including removal of slabs for tower cranes and hoists.
    • B-class hoarding / overhead gantry protection along Lavender St will be erected towards the end of October 2018.
    • Tower crane.  Targeting installation before Christmas 2018.

     

     

     

    Note the above are target dates and are subject to change.